The Primary Care Centre project at Clogherhead is an extension and upgrade of approximately 300 m2 to an existing primary care facility.

The project budget is approximately €500,000 and includes an occupational therapy unit and multi-use examination rooms, with the remainder being ancillary rooms. The M&E systems designed for the project included general services, lighting, nurse-call, fire-safety, access control and security, ICT, heating, water services and ventilation as well as soils and wastes. The design was completed to HTM and HBN standards.

During the construction phase relocation was necessary for some of the existing facility while the remainder continued in service. Our engineers have attended site meetings throughout, monitoring construction, commissioning and handover.

The construction phase is due to be completed in August 2016. The facility has been designed to an A3 BER rating.